Material Lead Times Run the Schedule

Ask a homeowner why their renovation ran long and you will usually hear something about the contractor. Ask the contractor and you will often hear about a delivery. Both can be true, but the delivery answer is the more common one, and it is the one that was decidable months earlier when nobody was thinking about schedule at all.
Scheduling begins with knowing who is involved and which portion of the sequence each trade owns. If you are still assembling that list, the Home Service Times directory is a reasonable starting point for how each specialty defines its own scope.
The Critical Path Is Usually a Box in a Warehouse

Project scheduling has a formal idea called the critical path: the sequence of dependent tasks whose total duration sets the minimum project length. On residential renovations that path frequently runs through a manufactured item rather than a trade. Cabinetry, made to order windows, custom glass, specialty tile, and anything requiring fabrication from a template all sit on it.
The practical consequence is that adding labor does not compress the schedule past the delivery date. A larger crew finishes the framing sooner and then waits. This is why a contractor's first meaningful question is often about selections rather than start dates, and why a homeowner who has not chosen cabinets is not actually ready to begin regardless of how complete the drawings look.
Order Sequence Beats Order Speed

Not everything can be ordered early. Countertops cannot be fabricated until cabinets are installed and templated, because stone is cut to the room as built rather than the room as drawn. Anything measured from finished conditions inherits the delay of whatever it is measured from.
That produces a natural ordering discipline. Long lead items with no dependencies go first, ideally before demolition. Items dependent on installed conditions get scheduled backward from their template date, and the template date is itself dependent on a trade completing. Laying this out on a single page early is unglamorous and saves more time than almost anything else available to a homeowner.
Confirm, Do Not Assume
Quoted lead times are estimates offered at the moment of quoting, and they move. The useful habit is to confirm at the point of order and again at the halfway mark, because a supplier who slipped four weeks will rarely volunteer that news early. A firm ship date is worth more than an optimistic one, and a substitution decided in week two is far cheaper than the same substitution forced in week ten.
Build the Float In
Schedules that assume every delivery lands on the promised day are brittle, and the failure is expensive because trades booked around a missing material either wait or move to another job and return when they can. A schedule carrying deliberate slack around the two or three longest lead items absorbs an ordinary delay without cascading.